People planning a build in Calpe usually ask how long it will take. We do not give a single answer, because the honest one depends on the plot, the licence and the weather. What we can do is set out the stages in order, so you know what is happening and why a stage may take longer than you hoped.
Stage one: paperwork before the first spade
A new house on an empty plot starts with a technical architect and a licence. The town hall decides what permission a project needs, so this stage is out of our hands and often out of yours. It is also the stage where delay is most common, so it is wise to start it early. For an extension or a flat, the community may also need to be consulted.
Stage two: the ground
It helps to treat the programme as a sequence rather than a single date. Each stage has to finish properly before the next one starts, and a build that skips ahead usually pays for it later.
Calpe's slopes mean the early work is about excavation, retaining structures and drainage. Falling land has to be held back and water led away, and this is not work to rush. Rain, when it comes, can be heavy and fast, so the programme has to allow for days when the site cannot be worked.
The same applies to a major renovation of an older villa. The first job is often to find out what condition the lower levels, roof and services are really in, and that can change the order of work.
Stage three: structure and roof
Once the ground is sound, the structure rises. Because salt and sun test every material here, the specification matters: reinforcement with proper cover, sealed surfaces, and details at the joint between old and new work if you are extending. A crack where an extension meets the house is a very common fault, and avoidable with care.
Stage four: the trades
With the shell closed, the trades follow in an order that suits the building:
- Plumbing and electrics, installed before walls are closed.
- Plastering and render.
- Tiling and flooring.
- Windows, doors, carpentry and kitchens.
- Painting and final fixing.
Our own plumbers, electricians, plasterers and tilers work to one programme, which avoids the gaps that come from waiting for separate firms.
What speeds a build up, and what slows it
- Decisions made early. Late changes to layout or finishes are the usual cause of delay.
- Access. A steep drive or a plot reached by a narrow road affects how materials arrive.
- Licences and consents. These sit with the town hall and, for flats, the community.
- Weather. Sun and heavy rain both interrupt exterior work.
Keeping in touch when you are not here
Many owners spend only part of the year in Calpe. We plan around that, with decisions taken in good time, photographs at each stage and video calls on site when a choice has to be made. We speak English and Spanish, and one project manager runs the job.
The free written quotation sets out the scope, and the work is guaranteed within the scope set out in the quotation.
Ready to get a free quote for your Calpe renovation project?
Visit Dragon Reforms →Why Choose Dragon Reforms
We're a local team covering Calpe and towns right across the Costa Blanca, with every project backed by clear pricing and fully insured, quality workmanship from start to finish.
Property Renovations Across the Costa Blanca
Dragon Reforms provides property renovation advice for homeowners throughout Calpe, Alfaz del Pi / Albir, Polop, Benidorm and Altea and towns right across the Costa Blanca.