No honest builder can promise a single finish date for a new home on a hillside, but the order of the stages is well understood. Knowing that order lets you see where the time goes and where a delay is likely to come from.

Stage one: the plot, before any design is fixed

On sloping ground the earth decides the programme. We are happy to visit a plot you are considering and say what building on it will involve, covering access, slope and groundwork. This is worth doing before money is committed to a design, because a steep Finestrat site can change what is sensible to build.

Stage two: paperwork and the project

Your architect prepares the project and the application. The town hall decides what permission is needed, and we never begin construction that requires a licence without it. This stage depends on other people's timetables, so it is the part we control least. Use it to settle layouts, finishes and levels, because changes become expensive once concrete is poured.

Stage three: groundwork

Excavation, retaining walls, foundations and drainage come first. They are the least visible and the most important, because trapped water behind a wall is what pushes it over. Steep access can limit machinery, so deliveries and storage are planned carefully, and hot or very wet spells can affect the work.

Stage four to six: from structure to finishing

  1. Structure and roof. The frame and walls rise, then the roof goes on so the house is closed against the weather.
  2. Services. Plumbing and electrics are installed before walls are closed. This is where the house starts to feel like a home on paper.
  3. Finishes. Plaster, tiling, joinery, windows and doors, then painting and fittings.

What stretches the timeline: approvals, weather and access

Approvals, ground conditions, deliveries of made-to-measure items such as glazing, and late changes of mind are the usual causes of delay. Decisions made early, and materials ordered in good time, are the most reliable ways of keeping a programme steady.

Finestrat has hot spells and heavy downpours, and both affect work on a hillside. A cement bed cures differently in extreme heat, and a wet spell can stop excavation altogether. On a steep drive, deliveries have to be arranged around what the lorry can reach, and materials need somewhere safe to be stored on the plot. We tell you what this means for the programme before the job starts, not once it is under way.

Handover and keeping in touch

When the finishing trades are done, we clean, check everything with you and walk through the house together, in person or by video. Snags are put right before keys change hands. Having a clear order of stages makes this last step calm rather than rushed.

Owners often ask what they can do to help. Decide the layout and levels early, choose windows and doors before the structure is built so that openings are formed correctly, and nominate one person who can answer questions quickly. Made-to-measure items arrive on their own schedule, so ordering them in good time keeps the trades from standing idle.

We run the excavation, structure, roof and finishing trades under one programme, with one person in charge. If you live abroad, you receive updates by phone and photographs, and we explain the reason before changing anything. The quotation we provide is free and separates groundwork from the building above it.

Ready to get a free quote for your Finestrat renovation project?

Visit Dragon Reforms →

Why Choose Dragon Reforms

Local team based on the Costa Blanca
Fully insured, quality workmanship
Free, no-obligation quotes
Clear pricing before any work starts

We're a local team covering Finestrat and towns right across the Costa Blanca, with every project backed by clear pricing and fully insured, quality workmanship from start to finish.

Property Renovations Across the Costa Blanca

Dragon Reforms provides property renovation advice for homeowners throughout Finestrat, Villajoyosa, Calpe, Alfaz del Pi / Albir and Polop and towns right across the Costa Blanca.