A fair answer to how long a new build takes is that the building itself is only part of the timeline. On a hillside plot in La Nucía a good deal happens before and around the construction, and several of those stages depend on other people. Here is the order things happen in, and where delays tend to come from.

Stage one: the plot

If you own a bare plot, the first step is a technical architect confirming what the land and local rules permit. Slope matters here: a plot that falls away may need retaining walls, levelling and careful foundations before anything rises. Urbanisations can have their own expectations about appearance and boundaries, and we ask about those early.

Stage two: drawings and permission

The project and licence application are prepared by an architect, and the town hall decides what permission is needed. We do not control that part of the programme, so it is the least predictable. We price against finished drawings, so that what you compare is real and not an estimate.

Stage three: groundwork and structure

  1. Clearing and levelling, with retaining walls where the slope requires them.
  2. Foundations, designed for the ground as found.
  3. The frame and walls, then the roof.
  4. Rough services run through the structure.

Weather and ground conditions can change this order. A wet spell on a slope can delay groundwork, and difficult access for deliveries to a hillside plot needs planning.

Stage four: first fix to finishing

Once the shell is closed we move through plastering, tiling, fitting and final painting. Waterproofing needs time to cure, and some materials are ordered to suit the design, so late choices on tiles, kitchens or windows are a common source of delay. Settle them early and the finishing runs far more smoothly.

During construction we run the structure, roof and finishing trades together, and that coordination saves more time than anything else. When the plumber, electrician, plasterer and tiler follow one another in order, nobody waits for a site that is not ready. Where an extension is being tied into an existing villa, the sequence also has to protect the rooms you already use, so we plan that from the start.

What speeds things up or slows them down

Think of the programme as a chain, not a single block of time. The early links, plot checks, drawings and permission, are the ones where we depend on others. The middle links, groundwork and structure, are mostly in our hands but at the mercy of weather and ground. The last links, finishing, are the ones you influence most through the decisions you make and when you make them. Asking for a programme that shows these separately gives a far more honest picture than a single date.

Keeping track from a distance

Many owners are away for long periods. We keep a record of every decision, send photographs and call with updates, so you arrive to find real progress. The quotation is free, and our work is guaranteed within the scope set out in the quotation. Ask for a programme alongside it and we will set out the order of stages for your plot.

Ready to get a free quote for your La Nucía renovation project?

Visit Dragon Reforms →

Why Choose Dragon Reforms

Local team based on the Costa Blanca
Fully insured, quality workmanship
Free, no-obligation quotes
Clear pricing before any work starts

We're a local team covering La Nucía and towns right across the Costa Blanca, with every project backed by clear pricing and fully insured, quality workmanship from start to finish.

Property Renovations Across the Costa Blanca

Dragon Reforms provides property renovation advice for homeowners throughout La Nucía, Finestrat, Villajoyosa, Calpe and Alfaz del Pi / Albir and towns right across the Costa Blanca.